考試題型是什么樣的?
沒改考綱版:目前考試題型是200道單選題,四選一,考試時長為4小時;
新考綱版:待確認(rèn)
PMP考試題是雙語的,中英文對照,英文在上,中文在下,所以不用擔(dān)心語言問題。
考試樣題:
While preparing the status report for stakeholders,the project manager discovers a negative
cost variance for a project where 10 percent of their work has been completed.What should the project manager do prior to meeting with the stakeholders?
A.Forecast the estimate at completion(EAC).
B.Initiate charge control procedures.
C.Put the project on hold until a response strategy is determined.
D.Use the contingency reserve.
1.在為相關(guān)方準(zhǔn)備狀態(tài)報告時,項目經(jīng)理發(fā)現(xiàn)一成本偏差為負(fù)數(shù),該項目 10%的工作己經(jīng)完成,在與相關(guān)方開會之前,項目經(jīng)理應(yīng)該怎么做?
A.預(yù)測完工估算(EAC).
B.啟動變更控制程序
C.擱置項目直到確定應(yīng)對策略
D.使用應(yīng)急儲備